a month ago
Hey, quick question - is there a way to freeze or pause a project so it stops billing but keeps all the config intact?
I have a project I won't be using for a couple of months, but I might come back to it later. Don't really want to delete it since setting everything up again would be a pain.
What's the best way to handle this?
Pinned Solution
a month ago
There is no way currently to pause your project. But there is a way to acheive the same result. You can remove the deployment (pause) and redeploy (unpause).
Steps:
1. Click on your Service Settings > Deployments.
2. Click on the three dots of your active deployment.
3. Select Remove.
When you want to "unpause" just go to Deployments and deploy the latest one.
3 Replies
a month ago
There is no way currently to pause your project. But there is a way to acheive the same result. You can remove the deployment (pause) and redeploy (unpause).
Steps:
1. Click on your Service Settings > Deployments.
2. Click on the three dots of your active deployment.
3. Select Remove.
When you want to "unpause" just go to Deployments and deploy the latest one.
a month ago
Note that you'll still be billed for storage (volumes/buckets).
a month ago
Thank you very much for your help