cost per service is incorrect

the cost per service (first image) doesn't sum up to the correct total? compared to project cost (second image)

project id: bcb473e2-e069-46f7-adab-4b2813985e93

Solved

8 Replies

Ping ☺️


dev
MODERATOR

10 months ago

!t


dev
MODERATOR

10 months ago

This thread has been escalated to the Railway team.

Status changed to Awaiting Railway Response dev 11 months ago


Railway
BOT

10 months ago

Hello!

We're acknowledging your issue and attaching a ticket to this thread.

We don't have an ETA for it, but, our engineering team will take a look and you will be updated as we update the ticket.

Please reply to this thread if you have any questions!


Status changed to Solved parmstar 11 months ago


jeremybarbet
PROOP

10 months ago

A few comments:

  • Is it normal the message above (railway[bot]) isn't showing up on discord?

  • Is it really "solved"? Because the math still doesn't adds up on my projects


Status changed to Open Railway 11 months ago


Railway
BOT

10 months ago

🛠️ The internal ticket Costs by Resource v Costs by Service don't add up has been marked as in progress.


Railway
BOT

10 months ago

✅ The internal ticket Costs by Resource v Costs by Service don't add up has been marked as completed.


jr
EMPLOYEE

10 months ago

This should be all fixed now! It was just a visual bug and didn't affect the amount you were billed.


brody
EMPLOYEE

10 months ago

!s


Status changed to Solved brody 10 months ago


Loading...