Service Metrics commit time overlay on graph is not right
sirhamy
HOBBYOP
2 years ago
On graph it says two commits happened today 2024.04.10 at 1901 and 1648 respectively.
However my repo has not received a commit since 2024.02.26 at 1141 and 1137 respectively.
I understand there may be time differences and I like the idea of the feature but the size and asymmetry of the incorrectness of these timestamps seems odd to me.
3 Replies
2 years ago
Have you redeployed the service today twice? That could be the two marks you are seeing.
Status changed to Solved Railway • almost 2 years ago
sirhamy
HOBBYOP
2 years ago
Ah that's it! They're deploy times and they're showing the latest commit I suppose.
Makes sense -thanks for quick response!